2017 Submission and Approval Schedule
Deadline Activity
April 21, 2017 Proposals due to TDA, end of business day
June 7, 2017 Potential sub-recipients notified of project state approval status
Oct 15, 2017 Sub-recipient will receive notification of USDA project approval status

2016 Schedule
2017
April 3, 2017 Progress Report Due
July 3, 2017 Progress Report Due
Nov. 15, 2017 Annual Report Due
2018
April 3, 2018 Progress Report Due
July, 3, 2018 Progress Report Due
Nov. 15, 2018 Annual Report Due
2019
April, 2, 2019 Progress Report Due
Aug 31, 2019 All grant funds must be used by this date
Oct. 31, 2019 Final Report Due
Projects can be completed prior to final report deadline with all supporting documentation being submitted within 30 days of project completion.

2015 Schedule
2016
April 1, 2016 Progress Report Due
July 1, 2016 Progress Report Due
Nov. 15, 2016 Annual Report Due
2017
April 3, 2017 Progress Report Due
July 3, 2017 Progress Report Due
Nov. 15, 2017 Annual Report Due
2018
April 2, 2018 Progress Report Due
Aug. 31, 2018 Grant Period Ends – all funds must be used by this date
Oct. 31, 2018 Final Report Due
Projects can be completed prior to final report deadline with all supporting documentation being submitted within 30 days of project completion.

2014 Schedule
2015
April 1, 2015 Progress Report Due
July 1, 2015 Progress Report Due
Dec. 1, 2015 Annual Report Due
2016
April 1, 2016 Progress Report Due
July 1, 2016 Progress Report Due
Nov. 10, 2016 Annual Report Due
2017
April 1, 2017 Progress Report Due
Aug. 31, 2017 Grant Period Ends – all funds must be used by this date
Oct. 31, 2017 Final Report Due
Projects can be completed prior to final report deadline with all supporting documentation being submitted within 30 days of project completion.