CM/GC Project I-55/SR-14

I-55 Exit Ramp to SR-14, SR-14 Bridge over I-55, SR-14 Bridges over CNIC R.R. & Nonconnah Creek

Design Consultant: Region 4 On-Call (Kimley-Horn)

ICE Selection: ICE TEAMS, LLC - 4/5/2024

CM/GC ICE Services

Notice of RFP Advertisement (Shelby County) - 7/28/2023

Addendum #1 - 9/1/2023

Addendum #2 - 9/8/2023

 

Q/R Response #1 - 9/1/2023

Q/R Response #2 - 9/8/2023

NOTICE TO CONTRACTORS REGARDING A REQUEST FOR PROPOSALS - 8/1/2023

Mandatory Pre-Proposal meeting was held on August 15, 2023

CMGC07 8-15-2023 Pre-Proposal Meeting Sign In

CMGC07 8-15-2023 Pre-Proposal Presentation

Sample Preconstruction Services Contract - 7/28/2023

CMGC07 AWARDED on 11/08/2023 - 11/13/2023

Reference Material - updated on 8/9/2023

128674.00 Project Map