Total capacity
once expansion is complete
|
2,400 |
|
Existing beds |
981 |
|
New beds |
1,444 |
| |
|
|
Estimated cost/construction
|
$144 million |
| |
|
|
Jobs created
|
250 |
| |
|
|
Construction
start date
|
Spring
2008 |
|
Estimated
completion |
Spring
2011 |
- By utilizing existing administrative staff, operational costs at
the facility will be significantly lower than if the department
had built a standalone facility.
- Upgrades will be made to regional water and electrical systems which will
benefit not only the prison but also the local community.
- Additional jobs created by the expansion will help put residents
of Bledsoe County to work. The current unemployment rate in
that county hovers at 10%.
- Experienced staff at Bledsoe County will ensure a stable
transition and dependable workforce.
- Cost of the expansion is far less than the other two building
projects being considered.