The State of Tennessee's Enterprise Resource Planning Solution

Logo of Project Edison

The State of Tennessee will Go-Live at the following Dates:

Human Capital Management Go-Live - October 1, 2008
Financials, Procurement and Logistics Wave #1 Go-Live - January 1, 2009
Financials, Procurement and Logistics Wave #2 Go-Live - April 5, 2009
Financials, Procurement and Logistics Wave #3 Go-Live - July 1, 2009

The Human Resources/Payroll modules will Go-Live on October 1, 2008. The State will deploy the Financials and Procurement / Logistics functionality in three waves. The first wave will deploy January 1, 2009, the second wave occuring April 1, 2009 and the third wave on July 1, 2009..