Roadway Activity Report for the Lower East and Upper Cumberland (March 7 - 13, 2024)

A complete list of lane closure activity due to construction or maintenance operation on state-owned roads within the 24 middle and east Tennessee counties of TDOT Region 2.
Monday, March 11, 2024 | 08:14am

DISTRICT 27

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution while traveling through the work zone.
[Jones Bros. Contractors, LLC/Crossville/CNV009]

 

CUMBERLAND COUNTY SR-1 (US-HWY. 70 W.) Utility Work both directions from LM 27.54 to LM 31.58: Shoulder and lane closures on SR-1 / US Hwy 70 from Renegade Mountain Parkway to Daysville Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/15/24 through 03/22/24 from 8 am - 3 pm. [2023-696]

 

CUMBERLAND COUNTY SR-1 (US-70) construction of a roundabout at SR-392 (LM 17 / Milo Lemert Parkway) and SR-101 (Peavine Rd / 17.4): Construction activities are ongoing. Motorists entering the roundabout should yield to vehicles within the roundabout. Motorists should use caution while driving through the work zone.
[Mack Construction, LLC/Crossville/CNW373]

 

CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Bridge replacement activities continue on SR-1 (US-70) over the Obed River bridge. SR-1 (US-70) is to be closed at the bridge for the duration of the project until the work is completed. A detour with signs have been displayed to utilize Northside Drive (SR-462) to travel around the closure. Additionally, the left turn from Sparta Drive onto Miller Avenue (SR-392) has been closed for the duration of the project. Motorists should be aware of the road closure and utilize the detour route as necessary. RESTRICTIONS: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72.
[Whaley Construction, LLC/Crossville/CNX110]

 

CUMBERLAND COUNTY SR-28 (US-127) grading, drainage, signals and paving from SR-68 to south of the bridge over Byrd's Creek (LM 9.7 to LM 10.6): Grading activities are in progress along SR-28 and SR-68. Traffic has been shifted to a section of the new alignment along SR-28 and SR-68. Construction equipment and vehicles will be entering and exiting the work zone frequently. Motorists should use caution when traveling through the area and be aware of the traffic pattern shifts.
[Cleary Construction, Inc./Crossville/CNW231]

 

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Activities will require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. Traffic has been swapped at Stout Drive intersection to near Cotton Patch Road. Motorists traveling west on Interstate Drive should be mindful of the "Right Turn Only" lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]

 

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. In addition, the contractor will be performing utility work adjacent to the existing alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]

 

CUMBERLAND, DEKALB, JACKSON, OVERTON, AND PUTNAM COUNTY Curb ramp upgrades in District 27: The Contractor will continue working in Putnam County on SR 136 from LM 2.31 to LM 4.15 weather permitting. During this work, the contractor will have a lane closure set up in the Northbound right lane of traffic and will also be working on the shoulder adjacent to the travel lane. Motorists are encouraged to use caution and follow construction signing. During this work sections of the sidewalk will be closed, and pedestrians will need to use an alternate route. The contractor is also scheduled to be on site installing signal loops in Overton County on SR 85 at LM 11.18. During this work, lane closures will be used, and motorists should be prepared to stop.
[MarCor Construction, Inc./Cookeville/CNX359]

 

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The East end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the West entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]

 

JACKSON COUNTY SR-135 rockfall mitigation north of Daniel Hill Lane (LM 7.1): The contractor has begun clearing and rockfall mitigation work. SR-135 is closed from LM 6.31 – 7.76. Message boards and detour routes are in place. Motorists are encouraged to use caution and follow detour signage.
[Tim's Tree Service, Inc./Livingston/CNX406]

 

JACKSON COUNTY SR-85 bridge repair over Indian Creek (LM 4.77): The contractor continues bridge repair work. The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone. A wide load detour is in place for vehicles that require larger clearance. Motorists are encouraged to use caution and watch for construction equipment and personnel throughout the work zone. RESTRICTIONS: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone.
[Thomson and Thomson, Inc./Livingston/CNX111]

 

PUTNAM COUNTY I-40 TDOT Maintenance both directions from MM 267.2 to MM 304: TDOT Maintenance Crews will be performing pothole repairs on I-40 from MM 267 to MM 304. Traffic will be reduced to one lane from 8 AM to 4 PM on Monday, March 11 and Tuesday, March 12. Traffic will be controlled using message boards and signing on I-40. Motorists are encouraged to use caution while travelling through the work zone.

 

PUTNAM COUNTY I-40 Utility Work both directions from MM 287 to MM 300: Law Enforcement Assisted Rolling roadblock will be performed on I-40 at Macedonia Cemetery Rd. Eastbound rolling roadblock will begin at MM 287 (South Jefferson Ave, SR-136 exit) and westbound will begin at MM 300 (S. Holly St, Monterey exit). Message boards, trucks, and law enforcement vehicles will be present along I-40 and ramps. Motorists should reduce speed, be prepared to stop, and expect delays. 3/10/24 from 6 am - 7 am, with a rain date of 03/17/24. [2023-428]

 

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Pigeon Roost Creek Road and Messenger Road are closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel.
[Rogers Group, Inc./Cookeville/CNV284]

 

PUTNAM COUNTY SR-135 (N. WILLOW AVE.) Utility Work both directions from LM 10.86 to LM 12.66: Shoulder and lane closure on N. Willow Avenue between W. Spring Street and N. Dixie Avenue. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 02/08/24 through 03/22/24 from 8 am - 3 pm. [2023-750]

 

PUTNAM COUNTY SR-136 (S. JEFFERSON AVE.) Utility Work both directions from LM 2.4 to LM 3.9: NIGHTTIME (8 pm - 6 am) and DAYTIME (9 am - 3 pm) shoulder and lane closures on South Jefferson Avenue between Interstate Drive and Stevens Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 09/15/23 through 03/29/24. [2023-336]

 

PUTNAM COUNTY SR-24 (W. SPRING ST.) Utility Work both directions from LM 14.34 to LM 18.57: Shoulder and lane closure on W. Spring Street/Broad Street between Willow Avenue and McBroom Chapel Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 02/08/24 through 03/20/24 from 8 am -3 pm. [2023-755]

 

PUTNAM COUNTY SR-290 (GAINESBORO GRADE) Utility Work both directions from LM 5.53 to LM 6.39: Shoulder and lane closure on Gainesboro Grade between N. Willow Avenue and Shipley Church Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 02/08/24 through 03/22/24 from 8 am - 3 pm. [2023-750]

 

 

DISTRICT 28

BLEDSOE COUNTY SR-28 LM 14.3 SIA route serving Project Protein: The contractor is constructing a new road for SIA serving Project Protein in Bledsoe County off of SR-28. A single right lane closure is setup on SR-28 SB from LM 14.2 to LM 14.4 to remove existing curb and gutter and replace with new. Please use caution when driving through the work zone.
[Twin K Construction/Dunlap/CNX188]

 

CANNON COUNTY SR-1 (US-70S) construction from near Barker Road (LM 1.2) to east of Hoover Road (LM 2.5): Contractor may be utilizing rolling roadblocks and lane closures through the work zone for signal work. On 03/07/24 there will be rolling roadblocks to hang span wire over SR-1 between 8 AM and 3 PM and SR-64 will have intermittent closures during this time. Motorists should remain vigilant of traffic control measures and use caution at the intersection of SR-64 and SR-1.
[Tinsley Asphalt, LLC /McMinnville/CNW348]

 

COFFEE, GRUNDY, AND WARREN COUNTY The ADA curb ramp upgrades on various State Routes: The contractor will have several shoulder and possible lane closures at various locations in Warren, Coffee, and Grundy Counties for sidewalk, signs, pavement marking, and ramp work. Motorists should use caution and watch for workers and equipment.
[MarCor Construction, Inc./McMinnville/CNX360]

 

SEQUATCHIE COUNTY SR-8 (HWY. 8) Utility Work both directions from LM 26 to LM 34: Mobile shoulder and lane closures between the intersection of SR-8 and SR-399 and ending at the intersection of SR-8 and George Hollands Lane as crews transition the work zone along the route. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 11/27/23 through 05/01/24 from 9 am - 2 pm. [2023-498]

 

WARREN AND WHITE COUNTY SR-136 repair of the bridge over the Caney Fork River LM 2: The bridge will be one lane through the duration of the project. Motorists should use caution and watch for flaggers. Motorists should expect some delays at the bridge with the traffic signal and traffic utilizing one lane.
[Jamison Construction, LLC/McMinnville/CNX109]

 
 

 

DISTRICT 29

BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will continue grading on the I-75 NB ramp off at Paul Huff Parkway. This work will take place behind temporary portable barrier rail. Left shoulder of Northbound exit ramp to Paul Huff Parkway will be closed for ramp construction. Motorists are advised to reduce speed and use caution in the work zone.
[Summers-Taylor, Inc./Cleveland/CNX362]

 

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will be working to remove the old bridge over Candies Creek and install new storm drainage. Intermittent flagging operations will take place at Campbell Drive during grading operations and storm drain construction. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.
[Summers-Taylor, Inc./Cleveland/CNV130]

 

BRADLEY COUNTY SR-311 (APD-40) Utility Work both directions at LM 2.58: Multi lane closures on SR-311 / APD-40 from Varnell Road to Industrial Drive SW / Refreshment Lane SW. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/29/24 through 03/14/24 from 9 am - 2 pm. [2023-727]

 

BRADLEY COUNTY SR-40 (US-64) resurfacing from SR-2 (US-11, US-64, LM 0.0) to near McKamy Street (LM 1.2): The contractor is closing SR-40 Westbound right lane from Bates Street to Edwards Street for the construction of a concrete island. This temporary closure will remain in place until the resurfacing is completed on SR-40 and permanent marking is in place for the new alignment.
[Wright Brothers Construction Company, Inc./Cleveland/CNX132]

 

BRADLEY, HAMILTON, MEIGS, RHEA, AND POLK COUNTY Curb ramp upgrades in District 29: During this reporting period, the contractor will be removing and replacing curb ramps in Bradley County along Inman Street from the intersection with Wildwood Avenue and on Ocoee Street. Pedestrian detour routes will be posted for any closed sidewalks. The contractor will continue to remove existing curb ramps in Polk County on SR68 from near Vine Street to Jackson Street. Shoulder and street parking closures are possible in this area as work to upgrade the curb ramps gets underway.
[Southern Constructors, Inc./Cleveland/CNX361]

 

HAMILTON COUNTY I-24 Utility Work both directions at MM 181: Shoulder and lane closure on 4th Avenue at the on and off ramps to 1-24. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 01 /23/24 through 06/30/24 from 8am - 5:30 pm. [2023-192/197]

 

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Nightly lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. Ramps have been modified or closed, and interstate traffic on both routes has been reduced to three lanes and moved toward the median to provide room for construction of new lanes, installation of drainage structures, retaining walls and bridges. Contract crews are working nightly so please stay alert for changing traffic conditions as construction vehicles enter and leave the roadway. To perform this work, rolling roadblocks may also be used in addition to lane closures to separate vehicles from construction activities. Multiple uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. Due to winter weather, it may be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day for patching potholes, clearing debris or to repair guardrail, attenuators, etc. The left lane on North and South Terrace between Belvoir Avenue and Spring Creek Road will be closed for installation of drainage structures, retaining and noise wall construction. Intermittent daytime non-rush hour lane closures may also be necessary throughout the period on South Terrace and North Terrace to work on utilities, street lighting, and various other construction items. All work is weather permitting. Moore Road and McBrien Road bridges over I 24 are closed as well as the entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road. A continuous flow detour using Belvoir Avenue and Spring Creek Road is in place for local traffic. The closures and detour will be in place for approximately 5 months. RESTRICTIONS: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

 

HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work both directions from LM 9.4 to LM 9.9: NIGHTTIME Interior Lane closures on E. 23rd Street between S. Lyerly Street and S. Orchard Avenue. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 03/04/24 through 03/13/24 from 7 pm - 7 am. [2019-507]

 

HAMILTON COUNTY SR-29 (US-27) Utility Work southbound at LM 22.26: Shoulder and single lane closure on SR-29 (Dayton Pike) between Coleman Rd and Highwater Rd. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present 3/7/24, 9 am to 2 pm with a rain date of 3/11/24 [2024-123]

 

HAMILTON COUNTY SR-321 (OOLTEWAH-RINGGOLD RD.) Utility Work both directions at LM 5.61: Shoulder and lane closures on SR-321 (Ooltewah-Ringgold Road) from Watkins Road to Apison Pike. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 02/29/24 through 03/13/24 from 9 am - 2 pm. [2024-072]

 

HAMILTON COUNTY SR-58 (MARKET ST.) Utility Work northbound at LM 4.21: Shoulder and single lane closure on SR-58 (Market St) between W. 20th Street and W 27th Street for aerial utility work. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present 3/12/24 -3/13/24 9 am to 2 pm [2023-656]

 

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The contractor on this project will have temporary lane closures on I-75 NB and SB from MM 4.0 to MM 7.0 for shifting traffic and installing portable barrier rail. Northbound and southbound entrance and on ramps from Shallowford Road will be affected for short durations from Thursday, March 7, 2024, through Wednesday, March 13,2024, 8 PM - 6 AM.
[Summers-Taylor, Inc./Chattanooga West/CNX358]

 

HAMILTON COUNTY SR-111 construction of two small drainage structures at LM 1.7 and LM 2.4: On SR111 Northbound and Southbound from LM 1.5-2.00, traffic will be down to 1 lane on SR111 as the contractor works on the project. The motoring public needs to be careful traveling this direction as workers will be present.
[Talley Construction Company, Inc./Chattanooga West/CNX344]

 

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility and grading work. The flagging operations will be performed on 03/07/24, 03/08/24, 03/11/24, 03/12/24 and 03/13/24 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment, and paving operations along the existing pavement.
[Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]

 

MCMINN COUNTY SR-2 (CONGRESS PKWY.) Utility Work southbound from LM 13 to LM 14: Shoulder and lane closures on SR-2 (Congress Pkwy) between Velma Road and Layman Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 01 /08/24 through 05/07 /24 from 7 am - 5 pm. [2023-412]

 

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
[Whaley Construction, LLC/Chattanooga East/CNX069]

 

MEIGS COUNTY SR-58 at SR-68 (LM 26.9) construction of a roundabout, and safety improvements on SR-58 near Nebo Road (LM 29.2): During this period, the contractor will be performing final sign installation for construction of a new roundabout. Intermittent lane closures are possible on SR-58 and SR-68 from 8 AM to 6 PM as work is performed. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Talley Construction Company, Inc./Cleveland/CNX073]

 

RHEA COUNTY SR-378 (S. MARKET ST.) TDOT Bridge Maintenance southbound at LM 0.91: Region 2 Bridge Maintenance will be repairing the wing wall at the culvert on S. Market Street over Richland Creek from Monday, March 11th - Tuesday, March 12th. Work will begin at 9AM with one lane closed. Traffic control will be in place.

 

 

REGION WIDE

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]

 

REGION 2 The installation of longitudinal cable barrier on various Interstate Routes: The contractor may have short term shoulder closures on I-75, I-24, and I-40 in order to perform cable rail installation. Both travel lanes will always remain open to traffic on the interstate during any work that is performed.
[R.D. Construction, LLC/McMinnville/CNW374]

 

REGION 2 The on-call concrete pavement repair at various locations on various Interstate and State Routes: The contractor will be repairing concrete pavement in Marion County in South Pittsburg beginning on 03/05/24 on SR-156/SR-27 between 1st St and 5th St. One direction of South Cedar Ave will remain open at all times. There will be multiple repair locations and detours will be setup as needed for closed sections of the road. Please follow detour routes and use caution when driving through the work zones.
[Vulcan Construction Materials, LLC/Dunlap/CNW379]

 

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Cumberland Guardrail, Inc./McMinnville/CNX096]

 

REGION 2 The random on-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will always remain open to traffic on the interstate during any work that is performed.
[Tennessee Guardrail, Inc./McMinnville/CNX312]

 

 

 

RESTRICTIONS

CUMBERLAND COUNTY - CNX110: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72.

JACKSON COUNTY - CNX111: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone.

HAMILTON COUNTY - DB2101: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed.

 

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.